Small missile ships Kozelsk and Okhotsk of project 22800 launched in Feodosia Reportedly, in Feodosia in the Crimea at the FSUE “Shipbuilding Plant“ More ”in October 2019, the first two small rocket ships“ Kozelsk ”built there under the control of JSC“ Leningrad Shipbuilding Plant “Pella” (serial number 254) and “Okhotsk” (serial number 255) of project 22800 (code “Karakurt”).
The lead Kozelsk small missile ship, which was being built at the More factory, (laid under the name Storm, serial number 254) was launched on October 9, 2019, and on October 17 it began towing from Feodosia along the inland waterways to the parent plant "Pella" (Otradnoe, Leningrad Region) for completion and testing. The second RTO "Okhotsk" (serial number 255) was launched on October 29 and will soon also be sent under tugboats for completion at the Pella.
Recall that project 22800 was developed by Almaz Central Marine Design Bureau JSC (St. Petersburg) and should actually replace in the construction for the Russian Navy the MRK of project 21631 (code "Buyan-M") developed by Zelenodolsk Design Bureau (JSC) ( construction of the latter is limited to 12 units so far). To date, the Russian Navy has contracted 18 RTOs of project 22800. The construction of the first seven RTOs of project 22800 is carried out by the Pella plant under the contract received in accordance with the order of the Government of the Russian Federation on obtaining this company the status of the sole supplier for this project.
The laying ceremony for the Russian Navy of the first two small missile ships of Project 22800 “Hurricane” (in 2018 it was renamed Mytishchi, serial number 251) and Typhoon (now called Sovetsk, serial number 252) was held at the Pella plant "December 24, 2015. The launch of the MRK “Hurricane” was carried out on July 29, 2017. The contract deadline for Hurricane was 2017. In fact, the Hurricane ship did not go to factory sea trials until May 17, 2018 and began the State trials on October 16, 2018. The ship was commissioned by the Baltic Fleet under the name Mytishchi on December 17, 2018.
The second Typhoon RTO (now Sovetsk) was launched on November 24, 2017, and began its mission on May 20, 2019, and on October 12, 2019, the ship was commissioned by the Russian Navy.
The third Shkval RTO (now called Odintsovo, serial number 253) was laid down at the Pella plant on July 29, 2016 and launched on May 5, 2018. On December 24, 2016, the fourth RTO of this Storm project (serial number 257) was launched at the Pella plant, launched on October 23, 2018.
Since the Pella plant acts as the main investor of FSUE Shipbuilding Plant More in Feodosia (Crimea), and in November 2016 received a part of the latter’s capacities for lease for a period until December 31, 2020, accordingly, out of the seven interregional distribution companies of the project 22,800 ordered "Pelle", three ships should be built at the Northwestern Federal District in close cooperation with Pella, which led to the transfer of the construction of three units to Feodosia. The first RTO of this project is "Storm" (now called Kozelsk, serial number 254) was laid in Feodosia May 10, 2016, and now October 9 launched and October 17, 2019 started towing main factory "Pella" for completion and testing.
The second RTO Okhotsk (serial number 255) was laid down in Feodosia on March 17, 2017, and launched on October 29, 2019. The third RTO "Whirlwind" (serial number 256) was laid down on December 19, 2017. RTOs being built in Feodosia received building numbers from 254 to 256 "in a row" of the building numbers for this project at Pella.
On August 22, 2018, the Russian Ministry of Defense entered into contracts for the construction of six more small missile ships of project 22800, which are intended for the Pacific Fleet. Four of them will be built at Amur Shipbuilding Plant JSC (NPS, Komsomolsk-on-Amur) with delivery in 2026, and two ships at Vostochnaya Verf JSC (Vladivostok) with delivery in 2023. The first two RTOs “Rzhev” and “Udomlya” of project 22800 with serial numbers 201 and 202 were laid at the NEA on July 1, 2019.
The serial construction of the RTOs of project 22800 is slowed down due to insufficient production rates of M507 diesel engines for them at PJSC Zvezda.
Small missile ship “Kozelsk” (laid down under the name “Storm” and while retaining this name on board, serial number 254) of project 22800 during towing along inland waterways from FSUE “Shipbuilding Plant“ More ”(Feodosia) for completion at AO” Leningrad Shipyard "Pella" (Otradnoye, Leningrad Region). Samara, 10.29.2019 (c) SlavaZ / fleetphoto.ruSmall missile ship "Okhotsk" (serial number 255) of project 22800 before launching at the FSUE "Shipbuilding Plant" More ". Feodosia, October 2019 (c) forums.airbase.ruhttps://bmpd.livejournal.com/3827424.html