2nd 20380 expected to launch in July.
Google translate wrote:- The construction of the second Project 20380 corvettes are now thrown all the forces - told the news agency "Khabarovsk region today," head of the department of the stocks of the Amur shipbuilding plant Ivan Hiz .
- Estimated ship date output from the workshop - 15 July.
At present, there are no problems in order to carry out all work in the set time frame.
Conducted enormous work on elektroosnascheniyu corvette shop works practically in two shifts.
Professionals need to build about 240 km of cables, the daily rate for stacking - 3 km a day, everything goes on schedule.
This work attracted workers from other plants, all aimed at to pass the patrol at the appointed time.